How should a Houston contractor keep the books: job costing, retainage and lien dates?
Houston contractor bookkeeping: cost every job, record retainage in two accounts, and keep Texas lien dates and sales tax contract type in your books.
By Yusuf Sezen · October 22, 2026 · United States · General information, not tax or legal advice.
Short answer: A Houston contractor should record every cost and invoice against a job, track retainage in two balance sheet accounts, and store notice and lien dates as job fields. For contracts entered on or after January 1, 2022, the enrolled text of Texas HB 2237 counts several Property Code Chapter 53 dates to the 15th of a later month. Confirm the current text with a Texas construction attorney.
This guide is for owners of Houston-area remodeling companies, general contractors and trade subcontractors (HVAC, electrical, plumbing, roofing, framing, flooring). After reading, you will know how to set up job records, show retainage and under-billing in your books, and keep Texas date and sales tax details next to each job.
This is bookkeeping information, not tax or legal advice. MusavirPlus is a bookkeeping service, not a CPA firm or a law firm. For tax decisions, ask a CPA or enrolled agent. For lien, notice and payment-timing questions, ask a Texas construction attorney.
Why can a Houston contractor's monthly profit and loss be misleading?
A monthly profit and loss report mixes three different things: what you billed, what you were paid, and what you earned. On jobs that last for months, those three numbers rarely match, so a month can look fine while one job quietly loses money.
Here is what each term means:
- Billed is the total of invoices you sent.
- Paid is the cash you actually received.
- Earned is the part of the contract price that matches the work done so far.
Retainage widens the gap. Retainage is a part of each progress bill that the customer holds back until a release point set in your contract. If you invoice $90,000 and the customer holds 10%, only $81,000 reaches your bank account, but the full $90,000 is still money you are owed.
The fix is not a bigger report. It is job-level records, which the next sections cover. Our monthly bookkeeping process follows the same idea: every transaction carries a job.
What should be on the job list before the first invoice?
Create one record per job with a unique job ID before you buy materials or send a bill. Every bill, receipt, payroll cost and invoice then carries that ID, which is what makes profit per job possible.
Most accounting software lets you do this with projects, classes or customer sub-accounts. Use whatever your software offers, but keep the same fields for every job. These fields matter most for a Texas contractor:
| Field | Why it matters in the books |
|---|---|
| Job ID, customer, address | Ties every cost and invoice to one place |
| County of the property | Section 53.052 of the enrolled text has lien affidavits filed with the county clerk of the county where the improvements sit (Harris, Fort Bend, Montgomery and others) |
| Contract type: lump-sum or separated | Decides where Texas sales tax lands (see below) |
| Residential or nonresidential | The enrolled Chapter 53 dates and the Comptroller tax rules differ by type |
| Contract amount and change orders | Needed for budget vs. actual and for the WIP schedule |
| Retainage percent and release condition | Tells you when to invoice the held amount |
| Date original contract was signed | HB 2237 applies only to original contracts entered on or after January 1, 2022 |
| Last month of work or delivery | The month that Chapter 53 dates are counted from |
If your chart of accounts is still generic, start with our chart of accounts guide and add the job cost accounts described next.
Which costs are direct job costs for a remodeler?
A direct job cost is any cost you would not have if you did not take that job. Code it to the job, not to general overhead. Overhead is the cost of running the company regardless of any one job.
Typical direct job costs for a Houston remodeler:
- Materials and supplies for that job
- Wages and payroll taxes of crew time spent on it
- Subcontractor invoices
- Equipment rental
- Permit, plan review and inspection fees you pay
- Dump fees and disposal
- Job-specific insurance and fuel
Typical overhead: office rent, software, owner's vehicle costs not tied to a job, general liability for the whole company, and office staff.
One common error is a single supply-house receipt booked entirely to "materials." If a receipt from a home improvement store covers three jobs, split it by line. Otherwise one job looks cheap and another looks expensive, and the job profit report is wrong.
If you pay crew through payroll and subs on Form 1099-NEC, keep them in separate accounts. For the 1099 rules, see our Form 1099-NEC guide. Franchise tax and field tickets belong to a different trade; for those, see our Houston oilfield contractor bookkeeping post.
How do you record retainage in the books?
Record retainage in two balance sheet accounts: "Retainage receivable" for money your customer holds from you, and "Retainage payable" for money you hold from your subcontractors. Neither one is revenue or expense; both are timing differences.
The usual flow for money held from you:
- Invoice the full progress amount, so revenue and the customer balance are correct.
- Move the held-back part from accounts receivable to retainage receivable.
- When the contract's release condition is met, invoice or request release, and move it back to accounts receivable.
- Record the cash when it arrives.
For money you hold from a sub, mirror it: record the sub's gross bill, move the held part to retainage payable, and clear it when you release it.
Add two fields to the job: the retainage percent and the release condition (for example, "final inspection passed"). Those words come from your contract. Contracts vary, so we cannot say what is typical.
Do not confuse this with the owner's statutory reserve. The enrolled text of HB 2237 says that during the work and for 30 days after it is completed, the owner shall reserve 10 percent of the contract price, or 10 percent of the value of the work done (Property Code 53.101(a)). That is a duty the law places on the owner. Contractual retainage is a payment term in your contract. They can be different amounts held for different reasons. Read the current Chapter 53 text or ask an attorney how they apply to you.
Retainage also shows why billed and paid differ. Your CPA decides the tax accounting method; the books just need billed and paid kept apart.
How do Texas notice and lien dates fit into job records?
Treat Chapter 53 dates as fields on the job card, not as events you remember. For contracts entered on or after January 1, 2022, the enrolled text of HB 2237 counts from a month and lands on the 15th day of a later month.
This section shows the pattern in the enrolled bill, for record-keeping only. We could not load the current codified Chapter 53 text from the Texas Legislature's statutes site when we checked, so confirm the current text there and ask a Texas construction attorney how it applies to your job. Later sessions may have changed it.
| Item (Property Code section) | Pattern in the enrolled HB 2237 text | Job card field to keep |
|---|---|---|
| Lien affidavit, original contractor (53.052(a)) | 15th day of the 4th month (projects other than residential) or the 3rd month (residential) after the month the original contractor's work was completed, terminated or abandoned | "Affidavit-by" date, once the completion month is known |
| Lien affidavit, other claimants (53.052(b), (c)) | 15th day of the 4th month (other than residential) or the 3rd month (residential) after the later of the month the claimant last provided labor or materials, or the month undelivered specially fabricated materials would normally have been delivered | Same field, per claimant role |
| Lien affidavit for retainage (53.052(d)) | 15th day of the 3rd month after the month the original contract was completed, terminated or abandoned | Retainage affidavit-by date |
| Notice of claim for unpaid labor or materials (53.056(a-1)) | 15th day of the 3rd month (other than residential) or the 2nd month (residential) after the month the labor or materials were provided | "Notice-by" date per month of work |
| Notice for unpaid retainage (53.057(a-1)) | The earlier of the 30th day after the claimant's contract is completed, terminated or abandoned, or the 30th day after the original contract is terminated or abandoned | Retainage notice date and the trigger event |
| Owner's reserve (53.101(a)) | 10 percent, during the work and for 30 days after completion | A note on whether the owner has a reserve |
The point for bookkeeping is simple: record the month you last worked or delivered, and the date your attorney or the statute says counts from it. Your role on the project decides which row applies.
Two more habits help. First, record whether notices were sent and how. The enrolled text of Section 53.003 lists delivery in person, by certified mail, or by another traceable private delivery or mailing service that can confirm proof of receipt, so keep the receipt or tracking number with the job. Second, track lien waivers per payment: which waiver you gave or received, for what amount, and on what date.
We do not calculate legal deadlines for clients or tell you whether to file anything. We keep the fields current and visible so you and your attorney can act.
How does Texas payment timing show up in your AR aging?
Put the due date from your contract on every invoice, then age receivables from that date. Texas Property Code Chapter 28 addresses payment timing for construction work on real property, but which rule applies depends on your contract and project, so ask an attorney.
Accounts receivable aging is a list of unpaid invoices grouped by how overdue they are, such as current, 1 to 30 days, 31 to 60 days and so on. For a contractor, keep three buckets visible:
- Invoices past their due date
- Retainage receivable and its release condition
- Work done but not yet billed (covered in the WIP section below)
If you and a customer disagree about part of an invoice, record the undisputed and disputed amounts on separate lines or notes. That makes it easy to see what is truly late.
Lump-sum or separated: how does the contract type change sales tax entries?
The contract type decides whether Texas sales tax on materials sits in your costs or in a liability account. Per the Texas Comptroller of Public Accounts, Publication 94-116, "Real Property Repair and Remodeling" (dated 03/2007), the rules differ for residential and nonresidential work.
Definitions first. A lump-sum contract has a single price for the entire job. A separated contract itemizes charges for materials and labor.
| Job type | What Publication 94-116 says | What you record |
|---|---|---|
| Residential, lump-sum | Contractor pays tax on materials, supplies, equipment and taxable services when buying them and does not charge the customer tax | Sales tax paid is part of job cost |
| Residential, separated | Contractor gives suppliers a resale certificate for materials that become part of the property, and collects state and local tax from the customer on those materials and certain separately identified services; construction labor is not taxable | Sales tax collected is a liability until paid to the Comptroller |
| Nonresidential repair or remodel | Total charged is taxable; contractor collects state and local tax on the total job charge | Sales tax collected is a liability; resale certificates kept on file |
For new residential construction, the Comptroller has a separate Publication 94-157 for homebuilders.
Sales tax rates depend on location. The Comptroller says the state rate is 6.25% and local taxes can add up to 2%, for a combined maximum of up to 8.25%. Use the Comptroller's rate locator for the rate at a specific job address.
The publication does not address when tax is due on progress bills or on retainage. Ask the Comptroller or a CPA about that. We record the contract type on the job, keep resale certificates on file, and track the tax collected or paid so your return preparer has clean figures. We do not tell you which contract type to choose.
What should you keep for each subcontractor?
Keep one file per sub with the same documents every time, so nothing is chased at year-end.
- Form W-9, Request for Taxpayer Identification Number and Certification
- Certificate of insurance and its expiration date, if your contract asks for one
- Signed subcontract
- Lien waivers given or received, by payment
- Payments year to date
- Retainage you hold from them
Worker classification, meaning employee or independent contractor, depends on the facts and not on what the paperwork says. The IRS page "Independent Contractor (Self-Employed) or Employee?" groups the evidence under behavior, finances and the type of relationship. Ask a CPA or enrolled agent if a worker's status is unclear.
What is a WIP schedule and what do over- and under-billing mean?
A work-in-progress (WIP) schedule is a monthly table that compares, job by job, how much you have earned with how much you have billed. Over-billing means you billed more than you earned. Under-billing means you earned more than you billed.
For each open job, the table needs:
- Contract amount, including change orders
- Cost to date
- Estimated cost to complete
- Percent complete (cost to date divided by total estimated cost)
- Earned revenue (percent complete times contract amount)
- Billed to date
- Over- or under-billing (billed minus earned)
How profit on long jobs is reported for tax is a tax-method question for your CPA. The books supply the cost and billing data.
Illustrative example: Bayou City Remodeling LLC
This is a made-up company with round numbers, to show the mechanics. It is not a tax or legal conclusion.
Bayou City Remodeling LLC has an owner, two W-2 carpenters and three subs. It has three open jobs on March 31.
| Job | Facts | What the books show |
|---|---|---|
| A: Kitchen remodel, residential, separated contract | Contract $80,000; billed $60,000; $22,000 of materials billed with sales tax collected | Sales tax collected sits in a liability account |
| B: Tenant build-out for a GC, nonresidential | Contract $150,000; billed $90,000 with 10% retainage held; paid $81,000. An electrical sub billed $20,000 and the company holds $2,000 | Retainage receivable $9,000; retainage payable $2,000 |
| C: Bathroom addition, residential, lump-sum | Contract $50,000; $10,000 deposit; cost to date $30,000; estimated cost to complete $12,000 | See the calculation below |
For Job C:
- Estimated total cost: $30,000 + $12,000 = $42,000
- Percent complete: $30,000 / $42,000 = about 71%
- Earned revenue: 71% of $50,000 = about $35,700
- Billed (the deposit): $10,000
- Under-billing: about $25,700
The $10,000 deposit is recorded as a customer deposit (a liability) until the work is done, not as revenue. The $25,700 shows up as work performed but not yet billed. A lender may ask for this figure, so the schedule is worth keeping current.
Lessons from the example: a month with cash in the bank can hide an under-billed Job C and $9,000 stuck in retainage. For Job B, the last month of work and the release condition are on the job card, so the owner knows when to ask for the retainage. And Job A and Job C land sales tax in different places.
What does a contractor's month-end routine look like?
Run the same steps every month, in the same order. The routine below adds contractor items to our general month-end close checklist.
- Reconcile bank, credit card and supplier-account statements.
- Post every supplier bill and receipt to a job, split by line where needed.
- Review uncoded transactions and clear them.
- Post payroll, with crew time by job.
- Age receivables, with retainage shown separately.
- Age payables, with retainage payable shown separately.
- Update the WIP schedule and look at over- and under-billing.
- Tie sales tax and payroll liability accounts to what was collected or withheld.
- Check job cards: last month of work, notices sent, waivers given and received.
- Print a budget vs. actual profit report per job.
For Houston-specific context, see our Houston bookkeeping page.
Frequently asked questions
What is retainage in construction bookkeeping?
Retainage is the part of a progress bill that a customer holds back until a release point in the contract. In the books, the held amount you are owed sits in retainage receivable, and the amount you hold from a subcontractor sits in retainage payable. The release condition and date belong on the job card.
Is retainage always 10 percent in Texas?
No. Contractual retainage is set by your contract. Separately, the enrolled text of HB 2237 describes a 10 percent owner reserve during the work and for 30 days after completion (Property Code 53.101(a)). Read the current text or ask an attorney how it applies.
What are the Texas lien deadlines for a subcontractor?
For contracts entered on or after January 1, 2022, the enrolled text of HB 2237 uses the 15th day of a later month, counted from a month set by the statute. Residential and other projects use different months, and the trigger depends on your role. Confirm with the current Chapter 53 text and a Texas construction attorney.
How fast must a Texas owner or contractor pay?
Texas Property Code Chapter 28 addresses payment timing for construction work, and the 1999 enrolled bill HB 1522 amended its payment deadlines. Which rule applies depends on your contract and project, so ask an attorney. In the books, record the due date from your contract on each invoice and age receivables from it.
Do I charge sales tax on remodeling in Texas?
It depends on the job. Per Comptroller Publication 94-116, residential lump-sum contracts mean you pay tax on materials, residential separated contracts mean you collect it on materials, and nonresidential jobs are taxed on the total charge. Confirm your situation with the Comptroller or a CPA.
How do I track profit for each job?
Give every job an ID, code every cost and invoice to it, and compare budget with actual each month. For long jobs, add a WIP schedule so billing is compared with work done. Software projects or classes can hold the job ID.
Do I need a Form 1099-NEC for my subcontractors?
Often yes, depending on the payments and the sub's business type. The thresholds and due dates are in the 1099-NEC guide linked above. Collect a Form W-9 before the first payment.
Can MusavirPlus file liens or give legal advice?
No. We are not a law firm or a CPA firm. We record your job, retainage, notice and waiver data in your books so you and your attorney or CPA have clean information. Details of our bookkeeping service for Houston businesses are on the Houston page above.
Sources
- HB 2237, enrolled text, 87th Legislature — Texas Legislature (checked 2026-10-22)
- HB 1522, enrolled text, 76th Legislature (Property Code Chapter 28 amendments) — Texas Legislature (checked 2026-10-22)
- Texas Property Code, Chapters 28 and 53 (current codified text) — Texas Legislature (page did not display the statute text when checked; confirm the current wording before relying on any date)
- Publication 94-116, Real Property Repair and Remodeling — Texas Comptroller of Public Accounts (checked 2026-10-22)
- Publication 94-157, Homebuilders — Texas Comptroller of Public Accounts (checked 2026-10-22)
- Sales and Use Tax — Texas Comptroller of Public Accounts (checked 2026-10-22)
- Independent Contractor (Self-Employed) or Employee? — Internal Revenue Service (checked 2026-10-22)
MusavirPlus provides bookkeeping only. We are not a CPA firm and do not prepare tax returns or give tax advice — for those, work with a licensed CPA, enrolled agent or (in Canada) a CPA.